NCN76 Manor Powis re-alignment

Stirling Council are working with Sustrans’ National Cycle Network (NCN) team to realign the NCN Route 76, diverting it from Alloa Road to an off-road path and quiet lane. This infrastructure will allow cyclists to bypass the Manor Powis roundabout and avoid on-road cycling along Alloa Road. The proposals also feature a connection to the new Walk, Cycle, Live Stirling active travel network at Causewayhead. This corridor addresses a key missing link for Sustrans, Stirling Council and Clackmannanshire Council, enhancing connections to Stirling City centre, Alloa, the University of Stirling and Causewayhead.


Thank you to everyone who took part in the design consultation. We have provided a summary of responses below.


In summary, there is a clear, strong support for the proposed active travel route. However, there are concerns from businesses and residents about the loss of parking on Alloa Road and equally concerns from others about the adequacy of the shared-use pavement if parking is not removed.


Our next steps are – as mandated through the consultation – to commit to deliver this “long-awaited, long overdue” active travel route. By progressing more detailed and technical designs for the concept presented between Manor Powis Roundabout – Ladysneuk Road (Phase 1). Share a timeline for delivery of this scheme, which will be subject to funding. Explore other options, interventions and alignments for the Alloa Road section of the route (Phase 2). 

A visualisation of Alloa Road looking east
A visualisation of ramp off the A91 looking west

Phases

Phases overview

Design period

1 January 2026 00:00 - 1 April 2027 23:00

We are currently working on completing the designs for Phase 1 of the route - between Manor Powis roundabout and Ladysneuk Road.

In this stage we will be working on:

  • Developing the designs (RIBA Stage 3 is due to complete in Summer 2026, RIBA Stage 4 is expected to be complete by early 2027)
  • Preparing application for construction funding bid (early 2027)
  • Securing planning permission (ongoing, outcome expected Summer 2026)
  • Finalising land negotiations (ongoing)

This work is programmed to conclude in March 2027. Construction is programmed for next financial year (2027/28), subject to the availability of external funding and land negotiations being concluded without significant delay.

Please find the finalised design for Phase 1 of the route below.

Upcoming and ongoing events

    0 events have loaded.
    No upcoming or ongoing events are currently scheduled.

    Past events

    • Event date: May 23rd, 2025 from 16:30 to 20:00.

      Location

      Allan Centre

      Registrants

      3 registrants

    • Event date: May 17th, 2025 from 10:00 to 15:00.

      Location

      Recyke-a-bike

      Registrants

      6 registrants

    2 events have loaded.